Dear buyers,
In addition to the ongoing work on defects in the apartments that have already been accepted, the following work is planned for this week on the various construction sites:
In construction site 2, the assembly of the oversized slabs for the terraces in houses 4 and 5 is still ongoing. In addition, the outstanding work by the HLS and ELT trades on construction sites 1 and 2 is to be completed this week and the already tolerated terrace slabs in houses 1 and 3 are to be completely laid become.
In addition to the ongoing assembly of the garbage room gates on construction site 1, the backfilling work on house 2 is also on the agenda.
For construction site 3, the plan this week includes, in addition to the scheduled drywall work in villas B1 and B2, the continuation of the HLS and ELT assembly in villa B2. In addition to the above-mentioned measures, the interior cleaning work in Villa B2 and the installation of the remaining window elements in Villa B1 are underway this week. Furthermore, a measurement of Villa B1 is created.
Last but not least, the earthworks and shaft work for drainage in construction site 3 will continue this week.
We wish you a good start to the week and look forward to your feedback.”