As you can see in the current picture, the work on the outdoor facilities is progressing well. The slab covering has been laid up to and including House 3.

In both construction areas, the terrain modeling is being continued, lattice stones are being placed, and the work of the clinker and painters is being completed. At the same time, the glass railings are transported to houses 1, 2 and 4 and prepared for installation.

BF 1
In construction site 1, reinforcement and plastering work on the facade, clinker brick work and remaining tiling work are being carried out on house 2.
Over the course of this week, the drainage channels, sockets and lights will be installed in the basement rooms, the cable trenches and cable pulls for the outdoor lighting will be made, the topsoil will be added for the planting areas and the terrace slabs will be transported.

BF 2
In construction site 2, the terrace slabs of house 4 will be laid this week, and the laying of the terrace slabs on house 6 will continue.

The processing of defects in the apartments that have been accepted continues to progress. As soon as the construction management notifies us of the defects in your residential units, we will contact you separately to accept them on site.

We wish you a pleasant and successful week and a nice start to spring 2023!