BF 1
This week, remaining work on the facade of house 2 will be carried out in construction site 1.
In addition, glass railings for House 2 will be transported over the apartment balconies.

BF 2
In construction site 2, the terrace slabs of house 4 are being laid and remaining work on house 6 is being carried out.
From houses 5 and 6 onwards, the oversized panels will be installed on the terraces this week.

BF 3
In construction site 3, the concreting of the underground car park entrance for Villa B1 is being prepared. Drywall work is also being carried out on Villa B1. This week the eaves will be installed in construction site 3. Furthermore, work is carried out on roof and terrace waterproofing, as well as earthworks and drainage shaft work.

The processing of defects in the apartments that have already been accepted is still in full swing.

We thank you for your trust and your patience. We wish you a pleasant and successful week!