Dear Sir or Madam, the work on defects in the apartments that have already been accepted continues to progress.
As soon as the construction management notifies us of the defects in your residential unit, we will contact you to carry out a declaration of defects together with you on site. Last week, the earthworks on the Augustastrasse boundary wall continued, so that the next step is to begin building the street-side wall on the foundations that have already been cast.

Erbacher & Kolb has now replaced all the locking cylinders on the house entrance doors and the underground car park doors so that the areas can be accessed with the apartment key.

BF1
The scaffolding around house 2 no longer exists, so that the drag strip for the necessary thermal insulation can be laid around house 2. In addition, the terrace tiles and glass railings for House 2 are transported over the apartment balconies and prepared for further laying.

BF2
The terrace slabs of house 4 are laid here. In addition, the laying work of the terrace slabs in houses 5 and 6 is in its final stages. In addition, the oversized slabs of the terraces of houses 5 and 6 will be installed.

BF3
Specifically, the concreting of the underground car park entrance for Villa B1 is being prepared. In construction area 3, the eaves will be installed, work will be carried out on the roof and terrace waterproofing, and earthworks and drainage shaft work will continue. We thank you very much for your trust and your patience. We wish you a pleasant and successful week!